Sorry we ran a little late on this update! Below are just a few of the many things going on behind the scenes with our building project.
TAKE 3: APRIL 2020
Below are some of the key target dates and activities we are working toward during the month of April:
- April 1-4 – BF team reviews general contractor (GC) proposal; calls GC references.
- April 6-10 – BF team submits follow-up questions to prospective GC’s.
- April 13-17 – BF team narrows down GC finalists; schedules interviews.
- April 20-24 – BF team conducts GC finalist interviews; makes GC selection.
- April 30 – Targeted completion of Structural, Lighting & MEP drawings
- April 30 – Prep site for underground utilities; curb & gutter