Below are just a few of the many things going on behind the scenes with our building project.
TAKE 4: MAY-JUNE 2020
Below are some of the key target dates and activities we are working toward during the latter part of May through the end of June:
- May 21 – GC selected – Batson-Cook Construction
- May 29 – GC pre-construction engagement commences
- June 01 – 80% plan set ready for initial building permit application
- June 05 – Waters systems and curb staking scheduled for completion
- June 26 – Site electrical conduits and irrigation sleeving scheduled for completion
- June 30 – Curb and gutter under way